Auditor finds ‘questionable’ land deals in Ahmedabad Metro Rail project

According to the independent auditor’s report, “It was observed that the GMRC did not have valid documents of the title deeds of a freehold land situated at Survey No. 525 at Kathwada..reports Asian Lite News

The Gujarat government on Friday put on record the details of the Ahmedabad-Gandhinagar Metro Rail project, where it was found by the internal auditor that land admeasuring around 20 hectares for the project was “questionable” in nature.

During the ongoing Budget session of the Gujarat Assembly, the Urban Development Department tabled the Gujarat Metro Rail Corporation (GMRC) Limited’s annual report for the year 2020-21.

According to the independent auditor’s report, “It was observed that the GMRC did not have valid documents of the title deeds of a freehold land situated at Survey No. 525 at Kathwada, Vastral in Ahmedabad, admeasuring 18,000 sq mt that is around two hectares, whose market value as on March 2021 was over Rs 16.82 crore.”

Other than that, the auditor also noted that land situated at final plot No. 56 and 285 at Ahmedabad Apperal Park (SEZ), admeasuring 17.62 hectares, was allotted by the Gujarat Industrial Development Corporation (GIDC) to the Metro company for the construction of a depot, “however the mode of transfer of this land from GIDC to the company has not been decided by the Gujarat government and according to the auditor, the land transfer is questionable”.

The Ahmedabad-Gandhinagar Metro was a dream project of Prime Minister Narendra Modi, the then Gujarat Chief Minister. The project was conceptualised initially in 2003 and it was put on a paper in 2005. After 16 years and umpteen number of route changes, the Corporation has been able to run it on only a 6 km stretch.

The 39.26 km stretch of Ahmedabad Metro Phase-1 project comprises two lines and 32 stations. It is being constructed at an estimated cost of Rs 10,773 crore.

GMRC is reportedly planning to commence trial lines in all sections of Line-2 by August, coinciding with 75 years of India’s Independence, and just ahead of the state elections scheduled to be held in December.

ALSO READ: Karnataka in a fiscal soup

Previous Story

Russia says buses ready to take out Indians  

Next Story

Factional rivalries rock AIADMK as Sasikala’s shadow looms over it

Latest from India News

Who Gets the Gloves for India 

Bangar feels it’s not feasible for India to play both Rahul and Pant in the same eleven, pointing out that the side can promote one of their spin-bowling all-rounders like Ravindra Jadeja

Jaishankar, UNGA Prez discuss UN agenda 

UNGA President Philemon Yang visits India for high-level talks with External Affairs Minister S Jaishankar, focusing on multilateral reforms and global cooperation.  External Affairs Minister S Jaishankar met Philemon Yang, President of

Exit polls predict BJP win in Delhi  

The exit polls, released after conclusion of polling in Delhi assembly elections, predicted that Congress is likely to continue its dismal run. ..reports Asian Lite News With most exit polls predicting that Bharatiya
Go toTop

Don't Miss

India, US to ink key semiconductor deal

The US Commerce Secretary has met with counterpart Piyush Goyal

Azad looking for ‘Hindustani’ name and flag for his party

Azad received a rousing reception from his political associates and